The University of Arizona
Planning, Design and Construction

Scottsdale Waterfront Phoenix Embassy Building

Description

Fit out of existing office building for use by the University of Arizona administrative units in the Greater Phoenix area.

Status

Substantial completion has been reached as of 7/7/23. Installation of furniture is underway.

Project Number
22-9579
Building Number(s)
Current Budget
$6,225,000
Projected Ultimate Budget
$6,225,000
Project Manager
Construction Project Manager
Construction Schedule
October 2022 - October 2022
Contractor
McCarthy Building Companies
Phase
Construction
Design Professional
Ayers Saint Gross
Delivery Method
Job Order Contract
GSF
15,000