El Portal Welcome Center Renovation
Description
3,800 GSF renovation to the 1st floor of El Portal. The renovation includes rooms 103, 104, 105, 105A, 106 and 108 to be remodeled into 3 offices, main lobby, space for work stations, lactation room and renovation to existing conference room.
Project Number
23-9675
Building Number(s)
182
Current Budget
$1,600,000
Projected Ultimate Budget
$1,600,000
Project Manager
Construction Project Manager
Construction Schedule
January 2024 - January 2024
Contractor
Lloyd Construction Co Inc
Phase
Occupancy
Design Professional
Breckenridge Group
Delivery Method
Job Order Contract
GSF
3,800