Center for Creative Photography, 2019 Remodeling and Renovations

Description

Renovate portion of first floor to create a multimedia gallery, renovate offices, and improvements to the environmental control system for Archives.

Status

Electrical work is complete. Special environment contractor is preparing for unit startup.

Project Number
19-9458
Building Number(s)
Current Budget
$3,447,200
Projected Ultimate Budget
$3,447,200
Project Manager
Construction Project Manager
Construction Schedule
January 2020 - June 2024
Contractor
D P R Construction, Inc., A General Partnership
Phase
Construction
Design Professional
Sears Gerbo Architecture
Delivery Method
Job Order Contract
GSF
9,063
VIEW SCHEDULE