Planning, Design and Construction

Education Building, 2nd and 3rd Floor Renovations

Description

The College of Education is implementing their Strategic Plan that will relocate Student Services to just inside the main entry of the Education Building.

Project Number
19-9461
Building Number(s)
69
Current Budget
$1,500,000
Projected Ultimate Budget
$1,500,000
Project Manager
Construction Project Manager
Construction Schedule
August 2021 - December 2021
Contractor
Kappcon
Phase
Occupancy
Design Professional
Line and Space, LLC
Delivery Method
Job Order Contract
GSF
2,000
VIEW SCHEDULE

Please try viewing in landscape mode.