Planning, Design and Construction

ECE Micro-Nano Center Renovation

Description

Renovate existing lab 316 infrastructure to support future programs.

Status

Generator installation is complete. New HVAC unit is installed and being started up.

Project Number
22-9595
Building Number(s)
104
Current Budget
$1,900,000
Projected Ultimate Budget
$1,900,000
Project Manager
Construction Project Manager
Construction Schedule
April 2023 - April 2024
Contractor
RW Burkel
Phase
Construction
Design Professional
Sears Gerbo Architecture
Delivery Method
Job Order Contract
GSF
11,240
VIEW SCHEDULE