CALS Animal Feeding and Resource Capture Facility

Description

This project will renovate an existing facility into a waste-to-energy research/teaching center involving anerobic digestion of bio solids and liquids .

Status

Design is in progress to renovate space in bldg. 2019.

Project Number
23-9641
Building Number(s)
2019
Current Budget
$10,150,055
Projected Ultimate Budget
$9,500,000
Project Manager
Construction Project Manager
Construction Schedule
June 2025 - July 2026
Contractor
Core Construction
Phase
Design
Design Professional
GLHN
Delivery Method
Design/Build
GSF
15,000
VIEW SCHEDULE