Planning, Design and Construction

BSRL Room 062 Tenant Imrpovement

Description

Renovations for equipment room for new MRI

Status

GMP amendment and approval in process. Construction scheduled to start in November 2024.

Project Number
24-9707
Building Number(s)
Current Budget
$1,175,000
Projected Ultimate Budget
$1,175,000
Project Manager
Construction Project Manager
Construction Schedule
TBD - TBD
Contractor
DPR
Phase
Design
Design Professional
ZGF
Delivery Method
CMR
GSF
0
VIEW SCHEDULE